According to three procedures, the EIA in Krivoy Rog refused to a positive conclusion
OVD/ 02.06.2020
According to three procedures of environmental impact assessment in Kryvyi Rih, enterprises have refused a positive conclusion. This happened due to imperfect or absent studies of the negative impact on air, water or soils. For reasons of lack of study …
ReadThe “Sukha Balka” was obliged to undergo an additional procedure of EIA on the mining of new horizons
OVD/ 02.06.2020
The “Sukha Balka” was obliged to undergo an additional procedure for assessing environmental impact on the mining of horizons 1500 and 1580 at the “Juvilejna” mine. Ministry relied on the conclusion to the public comments, first of all the SPKR, …
ReadAnswers “Arcelormittal” on the comments of the DTKR to the report from the EIA of the “IV map@ reconstruction
OVD/ 29.05.2020
“Arselormittal” gave the answers to the remarks of the SPKR to the report on ATS of reconstruction of tailing “IV map”. They are more like manipulation, hiding information, and other uncertain promises.
The enterprise reported that drainage system and a
Minkoenergo refused to give a positive conclusion to the EIA "AMKP" of construction of the "III map" tailing
OVD/ 29.05.2020
Minkoenergo took into account the remarks of the SPKR and other public organizations and refused in a positive conclusion with EIA «ArcelorMittal Kryvyi Rih». The company must carry out an additional assessment of the impact on the environment of construction …
ReadRemarks to the EIA report on the disclosure of Horizons 1500 and 1580 M of mine "Jubilee"
OVD/ 13.05.2020
Participants of “Stop Poisoning Kryvyi Rih” analyzed the report on environmental impact assessment on the disclosure of Horizons 1500 and 1580 M Mine “Juvilejna” of “Sukha Balka”. Public hearings on this occasion were held today, Feb. 19.
The discussions was …
ReadArcelorMittal Kryvyi Rih manipulates information during the ATS procedure
OVD/ 06.05.2020
ArcelorMittal Kryvyi Rih manipulates information during the ATS reconstruction procedure of the IV Card tailings pond with board extensions.
The participants of the DTCR studied the Environmental Impact Assessment Report of the planned activity and sent their remarks and comments …